STILI ROAD EOOD presented a report for successful completion of
Project BG16RFOP002-3.002-0078 „Enhancing the competitiveness of STILI ROAD Ltd, through implementation of energy efficiency measures”
Stili Road EOOD successfully completed the project „Enhancing the competitiveness of STILI ROAD Ltd, through implementation of energy efficiency measures” in the capacity of a beneficiary under the procedure “Increasing energy efficiency in large enterprises” BG16RFOP002-3.002 under Operational Programme “Innovations and Competitiveness” 2014 -2020, based on Grant Contract No. BG16RFOP002-3.002-0078 signed between Stili Road EOOD and the Ministry of the Economy, a part of which is the Directorate General European Funds for Competitiveness, designated as the Managing body of the Operational Programme “Innovations and Competitiveness” 2014-2020.
In pursuance of the grant contract, Stili Road purchased equipment consistent with the main project goal - „Making investments in new energy efficient equipment, which will ensure competitive and sustainable development of Stili Road EOOD in long-term aspect”
On 10.05.2019 Stili Road EOOD executed Contract BG16RFOP002-3.002-0078/Su-02 for delivery, installation and initial testing of one asphalt mixing plant in container design BENNINGHOVEN type ЕСО 2000 with WIRTGEN INTERNATIONAL GMBH, Germany. The value of the machines and equipment is BGN 3,461,820.
The plant consists of individual modules and elements, which in the technological sequence of the individual processes ensure production of different grades of bituminous concrete. The whole process is fully automated and is controlled on the basis of pre-set formulations and is operated only by one engineer - operator. The filter installation meets the highest environmental European standards and the production of the bituminous concrete does not produce harmful emissions in the air. The burner of the plant is fuelled by environment-friendly fuel - natural gas. The concrete mixer has additional plant for supply of 30% recycled concrete, which results in reduction of the generated construction waste in the process of construction as well as facility for production of bituminous emulsion. The mixing capacity of the plant is 160 tons per hour.
In pursuance of Contract № BG16RFOP002-3.002-0078/Su-01, Stili Road EOOD purchased two new wheel front loaders, make: HYUNDAI, model: HL960. The new machines have been installed and tested in Topoli village, Municipality of Varna, Asphalt Mixing Plant Stili Road EOOD. They have higher loading capacity, required for the higher capacity but have lower fuel consumption and respectively higher added value for energy savings.
The two wheel loaders have Declaration of Compliance issued by Hyundai Construction Equipment Europe N.V in accordance with: Machines Directive 2006/42/EC, Directive on electromagnetic compatibility ЕМС 2014/30/ЕО, Directive relating to emissions from non-road mobile machinery 97/68/EC (amended by 2002/88/EC, 2004/26/EC, 2006/105/EC) and relating to acoustic emissions 2000/14/EC (amended by 2005/88/EC). In this phase following performed technical and financial audit, the Managing body has verified total amount of eligible expenses of BGN 779,020, including BGN 389,510 financial aid and BGN 389,510 own financing.
The Project implementation will achieve the following key objectives:
Increasing the energy and resource efficiency; modernization of the manufacturing technologies; environmental protection; increasing the competitiveness of Stili Road EOOD
The ultimate value of Project № BG16RFOP002-3.002-0078 „Enhancing the competitiveness of STILI ROAD EOOD, through implementation of energy efficiency measures” is BGN 4 242 310.00 and the financial aid amounts to BGN 2 121 155.00.