On site: Major repair of municipal road VAR1087 /I-9/ Asparuhovo district - Galata district from the turnoff for the Karantinata area to the intersection with municipal road VAR3089 /I-9, Varna-Priseltsi/-Borovets ski resort-Galata district-Rakitnika ski resort-h. Chernomorets"Currently the curbs are being built using a new technology for the city of Varna - they are poured on site with a higher grade of concrete, which makes them stronger. The technology also allows for faster construction of the concrete elements.
After pouring the curbs, the construction of the sidewalks along the entire section of the road is to be completed. The sidewalks are between 2 and 3 meters wide on both sides, depending on existing buildings and facilities.
On the road from Asparuhovo to Galata, the entire section of the domestic sewage system and the sewage diversions have been built so far. Cement stabilization and rehabilitation of the road section have been carried out. The first layer of asphalt - binder has been laid on the roadway. Two more layers - binder and a dense mixture, with a total thickness of about 15 cm, are to be laid. The entire section of the road has a gauge of 7 meters.
It is also planned to build eight new stop signs, which will be stored in a pocket so as not to hinder traffic. There are no pockets for containers, because all household waste containers are located in the inner streets, which is coordinated with the waste collection company.
Client: Varna Municipality