"INGSTROYENGINEERING" Section from the end of the "Dermantsi" Road Junction (intersection with road III-307) to the intersection with road III-3005, incl. "Kalenik" Road Junction from km 119+260 to km 122+260. participates in the execution of LOT 2

28.11.2025

Object: Section from the end of the "Dermantsi" Road Junction (intersection with road III-307) to the intersection with road III-3005, incl. "Kalenik" Road Junction from km 119+260 to km 122+260

The construction of the "HEMUS" HIGHWAY is of national importance and a priority. The management and teams of "INGSTROYENGINEERING"  EOOD accept the construction of this site as a personal cause: The construction of the highway will not only contribute to the development of the economy in Northern Bulgaria, but will also significantly shorten travel time in the Danube Plain and connect the strategic regional centers - Sofia and Varna. Logistics in Northern Bulgaria will be faster, more comfortable and safer.

The execution of the section, which is with a gauge of 27m, falls within the "Lot 2" of the Hemus Highway. It covers the route from Dermantsi Road Junction to Kalenik Road Junction from km 103+150 to km 122+260.
According to the technical project, in the section from km 119+260 to km 122+260, three large facilities are being built (Viaduct at km 120+800, Agricultural underpass at km 121+300, Underpass at the "Kalenik" junction at km 121+771), 9 steel pipe culverts with a diameter of ф150 and 2 reinforced embankment walls.
Kalenik Road Junction is designed as a cloverleaf type. This road junction will provide a connection with the regional center of Lovech and the regional center of Pleven.
For drainage of the route and ensuring road safety from km 119+260 to km 122+260, 4 collector systems are also being built.

The section is key in the construction of a highway connection between central/western Bulgaria and Northern Bulgaria — with the potential to speed up travel, support economic development and the connectivity of the regions.